Work has started on the removal of the redundant paddling pool at the plant room.
We await input from Anglian Water regarding the disconnection of mains water. An order has been raised with UK Power to terminate the power, but we are unsure of their start date as yet. Neither of these will delay the removal of the paddling pool but will impact the demolition of the plant room.
The contractor confirmed that the provision of the new goal structures is on a 10-week delivery period. These will be installed prior to the tarmac surface works.